Seplat Energy Finalizes Gas Exchanger Upgrade Project

Seplat Energy Completes Major Inlet Gas Exchanger Replacement

Seplat Energy has successfully completed the replacement of the new Inlet Gas Exchanger (IGE) module on the East Area Project (EAP) platform, located in OML 67, offshore Nigeria. This significant milestone marks a key development in the company’s ongoing efforts to enhance its offshore operations and improve production efficiency.

The IGE module plays a crucial role in the Natural Gas Liquid (NGL) extraction process. It was the primary capital project for Seplat Energy’s offshore operations in 2025 and was completed within budget. The successful execution of this project underscores the company’s commitment to maintaining high standards of performance and safety in its operations.

Since the EAP complex was restarted, the facility has been operating in line with expectations. Gross NGL sales volumes at EAP have seen a remarkable increase, rising by over 100% to approximately 6,850 barrels of oil per day (bopd), or about 3,500 bopd on a net working interest basis. This is a significant improvement from the 3,360 bopd (~1,720 bopd net working interest) recorded in the nine months ending 30 September 2025. Further improvements are anticipated as the facility continues to reach its target efficiency levels, with expected NGL sales volumes reaching up to approximately 11,000 bopd (~5,700 bopd net working interest) in the coming months.

Key Project Activities and Safety Standards

The project involved a series of critical activities, including load-out, lifting, installation, tie-in, commissioning, and start-up. These tasks were carried out over a six-week period and were completed in November 2025. The entire project required over 2.2 million man-hours, all of which were completed safely, without any incidents, and to the highest industry standards.

Roger Brown, Chief Executive Officer of Seplat Energy, expressed his satisfaction with the project’s completion, stating, “We are pleased to have completed the first major capital project on our offshore operations on budget. Replacement of the IGE unit on our EAP platform builds on the success of our idle well recovery program as part of near-term production growth catalysts on the offshore assets that we acquired in December 2024.”

Strategic Importance of the IGE Module

The new IGE unit is essential for efficient NGL processing operations. NGLs, particularly pentane, represent some of the highest margin barrels produced in Seplat Energy’s portfolio. The butane produced is being sold directly into the domestic market, which helps improve energy access and supports initiatives aimed at promoting clean cooking solutions in Nigeria.

Brown added, “The successful completion of this project demonstrates the quality of our project and operations teams, the strong collaboration with our partners, the continued support of the local communities, and Seplat Energy’s commitment to drive growth offshore that will deliver value for Nigeria and our stakeholders.”

Future Outlook and Community Engagement

With the IGE module now fully operational, Seplat Energy is poised to achieve even greater efficiencies and output from the EAP platform. The company remains focused on sustainable growth and long-term value creation for its stakeholders while contributing to Nigeria’s energy needs.

The project also highlights the importance of community engagement and partnership in achieving operational success. Seplat Energy continues to work closely with local communities, ensuring that its operations align with the broader goals of economic development and environmental responsibility.