Port Harcourt — The Transmission Company of Nigeria (TCN) has initiated a significant rehabilitation project targeting two critical transmission corridors that supply electricity from the Afam power axis. This initiative is aimed at enhancing grid capacity and stabilising power supply in the South-South region.

The project involves the 38.6-kilometre Afam IPP–Port Harcourt and the 20.8-kilometre Afam IPP–Elelenwo 132kV double-circuit transmission lines. These lines play a crucial role in evacuating power from the Afam Independent Power Plants into the national grid. Their rehabilitation is expected to improve the efficiency and reliability of power distribution across the region.

Contractors were officially mobilised during a handover ceremony held over the weekend, marking the official start of the reconductoring works. This step signifies a major milestone in the company’s efforts to modernise its infrastructure.

Infrastructure Aging Poses Challenges

General Manager, Transmission Services, Engr. Ali Sharifai, highlighted the necessity of the 12-month rehabilitation project. He explained that the existing transmission infrastructure has aged significantly, leading to a gradual decline in wheeling capacity.

“The project has become imperative because the existing conductors have aged significantly, leading to diminished transmission efficiency and reduced wheeling capacity,” Sharifai said. His comments underscore the urgency of addressing the deteriorating state of the transmission lines.

Engr. Akpa Emmanuel, General Manager, Transmission, Port Harcourt Region, added that these lines are strategic assets within Nigeria’s power value chain. He emphasized their importance in evacuating bulk electricity from the Afam Power Plants to the national grid.

“These lines are central to transmitting power generated from the Afam Power Plants to the national grid,” Akpa said. “Once rehabilitated, they will significantly improve the reliability and stability of power supply within Port Harcourt and the wider region.”

Benefits of the Rehabilitation Project

According to Akpa, the reconductoring works will strengthen grid resilience, reduce transmission losses, and support improved power delivery as generation from the Afam axis increases. The project is expected to enhance the overall performance of the national grid, ensuring more efficient wheeling of generated power to distribution networks.

TCN stated that the rehabilitation aligns with ongoing efforts to modernise ageing transmission infrastructure. By upgrading these critical corridors, the company aims to increase the capacity of the national grid, making it better equipped to handle the growing demand for electricity.

Strategic Importance of the Project

The Afam power axis is a key source of electricity in Nigeria, and the rehabilitation of these transmission corridors is essential to maintaining a stable power supply. With the increasing reliance on this power source, the need for robust and efficient transmission infrastructure becomes even more critical.

The project also highlights the importance of continuous investment in the energy sector. As Nigeria strives to meet its growing energy demands, initiatives like this play a vital role in ensuring that the power generated can be effectively distributed to consumers.

Future Outlook

With the project now underway, TCN is expected to monitor progress closely to ensure that the rehabilitation is completed on time and within budget. The successful completion of this project could serve as a model for similar initiatives in other parts of the country.

By focusing on the rehabilitation of critical transmission corridors, TCN is taking a proactive approach to address the challenges posed by aging infrastructure. This effort not only supports the current power supply needs but also lays the foundation for future growth and development.

Conclusion

The rehabilitation of the Afam IPP–Port Harcourt and Afam IPP–Elelenwo transmission lines represents a significant step forward in improving the reliability and efficiency of Nigeria’s power grid. As the project progresses, it is anticipated that the benefits will extend beyond the immediate region, contributing to a more stable and resilient national energy system.